Goonyella Rail Expansion Project

The 924km Goonyella Rail System in Central Queensland services 30 coal mines in the northern Bowen Basin. Coal is railed to the Port of Hay Point, south of Mackay, where it is exported through the Hay Point Coal Terminal (HPCT), operated by the BHP Billiton Mitsubishi Alliance (BMA), and the Dalrymple Bay Coal Terminal (DBCT), operated by DBCT Management. 

Aurizon is currently investing $185 million in the initial stage of the Goonyella Rail Expansion Project. Initial projects will lift coal haulage capacity from 129 million tonnes per annum (mtpa) to 140 mtpa on the Goonyella System, the single largest export coal rail network in the country. The initial rail system upgrade by Aurizon will allow an additional 11 million tonnes per annum (mtpa) capacity on the network, assisting further growth of Queensland’s coal industry and the state economy, and supporting port expansion by BMA to lift the capacity at Hay Point Coal Terminal.  

Aurizon is also assessing further options for upgrading and expanding rail infrastructure on the Goonyella System across the Isaac and Mackay regions. Further details will be announced as projects are finalised. 

Under Construction 

Track Duplication south of Hay Point

Construction has commenced on the 7km track duplication south of Hay Point to service both Hay Point and Darymple Bay coal terminals. A holding track may also be necessary to provide additional capacity for empty trains required to travel back to Jilalan Yard. Benefits include streamlined operations and additional train holding capacity.


Second holding road construction South of Hay Point

Other projects not yet in construction

Wotonga Feeder Station

This project will replace the existing Track Sectioning Cabin (TSC) at Wotonga near Moranbah with a feeder station, and construct new TSCs in Carborough Downs and Grosvenor. Benefits include better power system reliability and more efficient train operations.

Contact Us

If you would like further information about the Goonyella Rail Expansion Project please contact the Aurizon Community Engagement Team.

T: 13 23 32 
E: community
@aurizon.com.au

Project Status

  • Under construction

Proposed Completion

  • Track Duplication South of Hay Point - Mid 2013
  • Wotonga Feeder Station - End 2013

Capital Costs

  • Approximately AU $185 million (for the intial phase)

Goonyella Rail Expansion Project Overview

Track Duplication South of Hay Point

Wotonga Feeder Station